| Year |
Key Events, Milestones and Major Achievements |
| 1977 |
IRBPL was incorporated as a private limited company. |
| 1977 to 1995 |
Execution of various construction contracts in the roads sector including World Bank aided projects as an EPC contractor. |
| September 1995 |
First venture in BOT Project being the signing of the Concession Agreement for Thane - Bhiwandi Bypass Phase - I. |
| June 1997 |
Completion of the construction activities in the Thane Bhiwandi Bypass Phase - I. |
| November 1997 |
Signing of the concession agreement for the Kharpada Project for construction of a bridge over river Patalganga on a BOT basis. |
| January 1998 |
Signing of the concession agreement for the Bhiwandi Wada project on a BOT basis. |
| July 1998 |
Incorporation of the Company as a private limited company. |
| September 1998 |
Signing of the concession agreement for the Thane Bhiwandi Bypass Phase II on a BOT basis. |
| November 1998 |
Signing of the concession agreement for the Khambatki Ghat project on a BOT basis. |
| December 1998 |
Signing of concession agreement for the Kaman Paygaon project on a BOT basis. |
| February 4, 1999 |
Completion of the Bhiwandi Wada project on a BOT basis. |
| July 20, 1999 |
Completion of the Kharpada Project Bridge over River Patalganga on a BOT basis. |
| March 25, 2000 |
Completion of the Kaman Paygaon project on a BOT basis. |
| August 15, 2000 |
Completion of the Khambatki Ghat project on a BOT basis. |
| January 2001 |
Signing of the joint venture agreement with Mudajaya Corporation of Malaysia for the execution of NHAI funded contract for the Ratanpur to Himmatnagar section of NH 8 for 54 kms. |
| January 2001 |
Signing of a funded EPC contract for the Ratanpur to Himmatnagar section of NH 8 for 54 kms with the NHAI. |
| November 2001 |
Signing of the concession agreement for the Ahmadnagar-Karmala-Temburni Road project on a BOT basis. |
| May 2002 |
Signing of an O&M and rehabilitation works contract with the NHAI for the Chiloda Naroda Section, Ahmedabad Bypass and the Ahmedabad -Vadodara Section of NH 8 in Gujarat. |
| May 2002 |
Signing of an O&M and rehabilitation works contract with the NHAI for Vadodara-Surat section of NH 8 in Gujarat. |
| May 2002 |
Signing of the concession agreement for the Mohol-Kurul-Kamti-Mandrup road on a BOT basis. |
| February 2003 |
Signing of the concession agreement for the Pune Sholapur Project on a BOT basis. |
| August 25, 2003 |
Completion of construction activities in the Ahmadnagar-Karmala-Temburni Road project on a BOT basis. |
| August 2003 |
Signing of the concession agreement for the Pune Nashik project on a BOT basis. |
| December 2003 |
Completion of the construction activities in Thane Bhiwandi Bypass BOT project - Phase II. |
| January 2004 |
Completion of the construction activities for the funded EPC Contract for the Ratanpur to Himmatnagar Section of NH 8 for 54 kms. |
| May 2004 |
Emerged as the highest bidder for Mumbai-Pune Expressway project by making upfront payment of Rs. 918 crore to MSRDC for concession rights for a period of 15 years. |
| August 2004 |
Signing of the concession agreement and financial closure of the Mumbai Pune Expressway project of Rs. 1,181.41 crore. |
| August 2004 |
Commencement of construction activities of the NH 4 and commencement of toll collection on the Mumbai Pune Expressway. |
| December 10, 2004 |
Completion of construction activities for the Pune Sholapur BOT project. |
| April 2005 |
Commencement of construction activities on the O&M on Mumbai-Pune Expressway as BOT operator. |
| July 2005 |
Signing of the concession agreement with the NHAI for the the four-laning of (a) km 64-000 to km 94-000 and (b) Km 123 to km 153 of the Nagpur-Hyderabad section of NH 7 in the State of Maharashtra. |
| November 2005 |
Emerged as the highest bidder for the Thane Ghodbunder project by offering a negative grant of Rs. 140.40 crore to the MSRDC for concession rights for a period of 15 years. |
| December 20, 2005 |
Completion of the construction activities for the Pune-Nashik Project. |
| December 2005 |
Signing of the concession agreement and financial closure of the Thane Ghodbunder project with financing of Rs.216.60 crore and commencement of toll collection. |
| July 2006 |
Signing of the concession agreement for the Bharuch Surat project on a BOT basis. |
| September 2006 |
Commencement of toll collection on Mumbai- Pune NH 4. |
| December 2006 |
Achieved financial closure of the Bharuch Surat project with financing of Rs. 1,210.95 crore. |
| December 2006 |
Payment of a negative grant to NHAI of Rs. 504 crore in respect of the Bharuch Surat project. |
| January 2007 |
Formed a consortium with Deutsche Bank AG, Singapore to jointly pre-qualify for eight packages of four to six laning under NHDP V. |
| February 2007 |
Awarded the contract by the Ahmedabad Municipal Corporation for the construction of Janmarg (Bus Rapid Transport System Project) from Narol Circle to Naroda Patiya in Ahmedabad for a total project cost of Rs. 132.99 crore. |
| April 2007 |
Balance work of construction of Tapi Bridge amount to Rs. 44.15 crore was awarded as an additional scope of work to Bharuch Surat BOT Project |
| June 2007 |
Awarded the funded contract by the Ahmedabad Municipal Corporation for construction of Janmarg (Bus Rapid Transport System Project) from Pirana-Danilimada-Maninagar-Narol in Ahmedabad for a total project cost of Rs. 78.36 crore. |
| July 2007 |
Successfully Completed the construction phase of the Thane-Ghodbunder project. |
| September 2007 |
Granted "pre-qualified" status that entitled the IRB Group to submit request for proposals for certain NHDP Phase V road infrastructure projects; namely, the Chennai-Tada project on NH 5, the Gurgaon - Kotputli - Jaipur project on NH 8, the Surat - Dahisar project on NH 8, the Chilkaluripet - Vijayawada project on NH 5 and the Panipat - Jalandhar project on NH 1. |
| September 2007 |
Acquisition of shares in IRBPL, IRB Infra, NKT, TGTRPL and MIPL making them wholly-owned Subsidiaries of the Company. |
| November 2007 |
Submitted bids for the Gurgaon - Kotputli - Jaipur project on NH 8 and the Surat - Dahisar project on NH 8. For further information, see "Business-Our BOT Infrastructure Development Projects - Recent Developments" on page 83 of this Prospectus |
| December 2007 |
Submitted a bid for a BOT project relating to the Integrated Road Development Program in Kolhapur. |
| January 2008 |
Company has launch its Initial Public Issue duing 31st January 2008 to 5th February 2008. The issue was oversubscribed by 4.3 times. Issue price thereafter was fixed at Rs. 185/- per share |
| February 2008 |
Declared as Successful Bidder for the Project of " Six Lanning of Surat - Dahisar section of NH-8 from Km 263.00 to Km 502.00 (Length - 239 Km ) in the state of Gujarat / Maharashtra to be executed as BOT (Toll) basis on DBFO Pattern under NHDP Phase - V" |
| February 2008 |
Company was listed on Bombay Stock Exchange and National Stock Exchange on 25th February 2008 |
| February 2008 |
Declared as Successful Bidder for the project of " Integrated Road Development Programme (IRDP) for Kolhapur City" |
| April 2008 |
Concession Agreement for 6 - Laning of Surat - Dahisar BOT Project on DBFO pattern has been executed on 30th April 2008 Between National Highways Authority of India and IRB Surat Dahisar Tollway Private Limited at New Delhi
|