News & Events
IRB has emerged as lowest bidder for a Amritsar to Panthanko BOT Project of NHAI
IRB has emerged as the lowest bidder for a BOT project comprising Design, Engineering,
Finance, Costruction, Operation amd Maintenance of Pathankot to Amritsar Section
of NH - 15 from Km.6.082 to Km. 108.502 in the State of Punjab under NHDP Phase
IIIB on BOT Basis. The Construction cost is approx. Rs. 1200 crores. The
project length is 102 Kms. IRB gets a concession period of 20 years and the equity
support from NHAI during construction phase demanded is Rs.126.90 crores. The construction
period is 910 days.