Ahmedabad - Vadodara BOT Project
 

Name of the Project Six Laning of Ahmedabad to Vadodara Section of NH 8 From Km. 6.400 to Km 108.700 (Length 102.300 Km) in the state of Gujarat and Improvement of existing Ahmedabad Vadodara Expressway (NE-1) from Km 0.000 to Km 93.302 in the state of Gujarat (Length 93.302 Km) under NHDP Phase V on Design, Build, Finance, Operate, Transfer (DBFOT) Toll Basis.
Client / Employer National Highway Authority of India
Name of the SPV IRB Ahmedabad Vadodara Super Express Tollway Private Limited
Date of Signing of Agreement 25th July 2011
Project Cost ( Estimated ) Total Project Cost = Rs 48800.00 Million

Project was on premium basis. First Year premium to be paid to NHAI is Rs. 3096.00 million which will be increased by 5% year on year.
Financers of the Project
  • IDFC Limited ( Lead Bank),
  • Punjab National Bank
  • ICICI Bank Limited
  • Andhra Bank
  • Bank of India
  • Indian Overseas Bank
  • Union Bank of India
  • IIFCL
    FC Achieved
  • Construction Period 36 Months
    Date of Start Appointed Date is yet to be issued by NHAI
    Schedule Date of Completion 36 Months from Appointed Date
    Concession Period 25 Years
    Concession Period ends on 25 Years from Appointed Date
    Total Length NH-8 = 102.300 Kms
    NE -1 = 93.302 Kms
    Total = 195.602 Kms
    Scope of Work

    Ahmedabad Vadodara NH-8

    Six Laning of Main Carriageway - 102.300 Kms
    Construction of Service Road – 82.50 Kms
    Construction of Slip Road – 43.58 Kms
    Improvement to Minor Junctions - 124 Nos.
    Improvement to Interchanges – 1 Nos.
    Construction of new Flyovers – 15 Nos.
    Construction of ROBs – 4 Nos.
    Construction of Major Bridges - 4 Nos.
    Construction and rehabilitation of Minor Bridges - 27 Nos.
    Construction of Underpasses ( PUB, CUP & VUP) – 23 Nos.
    Construction and widening of Culverts - 186 Nos.
    Providing Entry and Exit Ramps – 14 Nos.
    Construction of Truck Lay Bye – 6 Nos.
    Construction of Bus Bays – 32 Nos.
    Construction of new Toll Plaza – 2 Nos.
    Providing 2 Mtr Walkway for “ Dandi Heritage Route” – 13.3 Kms
    Providing Highway Traffic Management System
    Operation and Maintenance till end of Concession Period

    Ahmedabad Vadodara Expressway – NE 1

    Improvement and Strengthening of Carriageway – 93.302. Kms
    Additional Span to Sheddhi river Bridge
    Improvement to existing Bridges
    Maintenance of Chute Drains
    Providing BOX / Slab / Pipe Culvers – 8 Nos.
    Providing Longitudinal aggregate drain to entire length of expressway
    Improvement to existing Toll Plaza – 5 Nos.
    Providing Highway Traffic Management System
    Operation and Maintenance till end of Concession Period